Reform Impact

Karachi

Time: Number of days down from 260 to 92 days.

Procedure: Down to 7 from 18

Cost: Reduced to PKR 448,000 from PKR 695,175.

Reform Impact

Lahore

Time: Number of days down from 260 to 70 days.

Procedure: Down to 8 from 20

Cost: Reduced to PKR 170,650 from PKR 311,150

 

What it Measures?

Procedures, time and cost to complete all formalities to build a warehouse and the quality control and safety mechanisms in the construction permitting system.

How to apply for a Construction Permit

Getting a Construction Permit for a business is easy via online portals.

Getting a Construction Permit in Sindh

You can apply for construction permit in Sindh from Sindh Building Control Authority.

Getting a Construction Permit in Punjab

Apply for a construction permit with ease at e-Khidmat Markaz or through Lahore Development Authority offices.

Reform Actions