Step 1

Submit application to K-Electric Ltd. and await site inspection

Duration: 2 Days

Cost: PKR 200

Step 2

Obtain site inspection by K-Electric Ltd. and await estimate

Duration: 13 Days

Cost: Nil

Step 3

Obtain wiring inspection

Duration: 3 Days

Cost: PKR 10,000

Step 4

Pay estimate to K-Electric Ltd., and submit the internal wiring test report as well as the delivery orders of the material

Duration: 30 Days

Cost: PKR 2,701,421

Step 5

Await external works, meter installation and electricity flow from K-Electric Ltd.

Duration: 53 Days

Cost: Nil

Approximate Procedure Time : 125 Days

Approximate Cost: PKR 2,711,621

Step 1

Submit application to LESCO and await site inspection

Duration: 30 Days

Cost: Nil

Step 2

Obtain site inspection by LESCO and receive estimate

Duration: 30 Days

Cost: Nil

Step 3

Obtain wiring inspection

Duration: 3 Days

Cost: PKR 1,480

Step 4

Pay estimate to LESCO, and submit the internal wiring test report

Duration: 1 Day

Cost: PKR 875,870

Step 5

Receive external works and await final inspection

Duration: 28 Days

Cost: Nil

Step 6

Receive inspection of external works, meter installation and electricity flow from LESCO

Duration: 14 Days

Cost: Nil

Approximate Procedure Time : 96 Days

Approximate Cost: PKR 877,350

Procedure for Karachi

Step 1

Submit application to K-Electric Ltd. and await site inspection

Duration: 2 Days

Cost: PKR 200

Step 2

Obtain site inspection by K-Electric Ltd. and await estimate

Duration: 13 Days

Cost: Nil

Step 3

Obtain wiring inspection

Duration: 3 Days

Cost: PKR 10,000

Step 4

Pay estimate to K-Electric Ltd., and submit the internal wiring test report as well as the delivery orders of the material

Duration: 30 Days

Cost: PKR 2,701,421

Step 5

Await external works, meter installation and electricity flow from K-Electric Ltd.

Duration: 53 Days

Cost: Nil

Approximate Procedure Time : 125 Days

Approximate Cost: PKR 2,711,621

Procedure for Lahore

Step 1

Submit application to LESCO and await site inspection

Duration: 30 Days

Cost: Nil

Step 2

Obtain site inspection by LESCO and receive estimate

Duration: 30 Days

Cost: Nil

Step 3

Obtain wiring inspection

Duration: 3 Days

Cost: PKR 1,480

Step 4

Pay estimate to LESCO, and submit the internal wiring test report

Duration: 1 Day

Cost: PKR 875,870

Step 5

Receive external works and await final inspection

Duration: 28 Days

Cost: Nil

Step 6

Receive inspection of external works, meter installation and electricity flow from LESCO

Duration: 14 Days

Cost: Nil

Approximate Procedure Time : 96 Days

Approximate Cost: PKR 877,350