Step: 1

Obtain letter from the relevant land owning authority confirming the land title

Duration: 14 Days

Cost: Nil

Step: 2

Obtain building permit from SBCA

Duration: 30 Days

Cost: Rs. 224,000

Step: 3

Notify the Sindh Building Control Authority (SBCA) in writing of the completion of foundations

Duration: 1 day

Cost: Nil

Step: 4

Receive foundations work inspection from the Sindh Building Control Authority (SBCA) and await approval

Duration: 15 Days

Cost: Nil

Step: 5

Apply for occupancy permit and request final inspection from SBCA

Duration: 1 Day

Cost: Nil

Step: 6

Receive final inspection from SBCA

Duration: 1 Day

Cost: Nil

Step: 7

Receive completion certificate from the Sindh Building Control Authority (SBCA)

Duration: 30 Days

Cost: Rs. 224,000

Step: 1

Customer submits completed documents at Customer Facilitation Centre

Step: 2

Download challan from website and pay fees at Bank of Punjab

Step: 3

Customer will receive a message from Customer Facilitation Centre to collect sanction letter

Step: 4

Notify Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA) in writing of the completion of foundations

Step: 5

Receive foundations work inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 6

Submit the first floor Certificate Form to the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 7

Receive first floor slab casting inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 8

Submit the second floor Certificate Form to the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 9

Receive second floor slab casting inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 10

Apply for completion certificate and request final inspection

Step: 11

Receive final inspection

Step: 12

Receive completion certificate from Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

50 Days

Procedure Time (Approximately)
Procedure for Karachi

Step: 1

Obtain letter from the relevant land owning authority confirming the land title

Duration: 14 Days

Cost: Nil

Step: 2

Obtain building permit from SBCA

Duration: 30 Days

Cost: Rs. 224,000

Step: 3

Notify the Sindh Building Control Authority (SBCA) in writing of the completion of foundations

Duration: 1 day

Cost: Nil

Step: 4

Receive foundations work inspection from the Sindh Building Control Authority (SBCA) and await approval

Duration: 15 Days

Cost: Nil

Step: 5

Apply for occupancy permit and request final inspection from SBCA

Duration: 1 Day

Cost: Nil

Step: 6

Receive final inspection from SBCA

Duration: 1 Day

Cost: Nil

Step: 7

Receive completion certificate from the Sindh Building Control Authority (SBCA)

Duration: 30 Days

Cost: Rs. 224,000

Procedure for Lahore

Step: 1

Customer submits completed documents at Customer Facilitation Centre

Step: 2

Download challan from website and pay fees at Bank of Punjab

Step: 3

Customer will receive a message from Customer Facilitation Centre to collect sanction letter

Step: 4

Notify Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA) in writing of the completion of foundations

Step: 5

Receive foundations work inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 6

Submit the first floor Certificate Form to the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 7

Receive first floor slab casting inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 8

Submit the second floor Certificate Form to the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 9

Receive second floor slab casting inspection from the Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

Step: 10

Apply for completion certificate and request final inspection

Step: 11

Receive final inspection

Step: 12

Receive completion certificate from Metropolitan Corporation Lahore (MCL) or Lahore Development Authority (LDA)

50 Days

Procedure Time (Approximately)